Foundry Avenue Replacement Project

Scope: Sharpshill Road to mid-block of Foundry Avenue

Installation of 1070 LF of 6″ PVC mainline to replace aged waterline on Foundry Avenue in Shaler Township, from Sharpshill Road to a fire hydrant mid-block where newer pipe picks up.

 

The work is scheduled to start construction in mid September and take 5 weeks to complete.

Church Avenue Replacement Project

Scope: Mount Royal Boulevard to Bleil Drive

Installation of 920 LF of 6″ PVC mainline to replace aged waterline on Church Avenue in Shaler Township, from Mount Royal Boulevard to the end of Church Avenue and through the paper street down to Bleil Drive.

 

The work is scheduled to start construction in early September and take 5 weeks to complete.

Burchfield Road Replacement Project

Scope: Willruth Drive to the Burchfield Booster Station

Installation of 2,050 LF of 8″ PVC mainline to replace aged waterline on Burchfield Road in Shaler Township, from Willruth Drive (at Pizzarita) to the Burchfield Booster Station (just past Victory Road).

BURCHFIELD 2

This work will be constructed using bond monies from our 2015 Bond Issue.  The work is scheduled to start construction in mid-June 2017 and take 6 weeks to complete.